Can an arbitral tribunal grant extra payment for materials used in a lump-sum contract?

Court sets aside arbitral award for payment of excess cement in lump-sum construction contract.

The Delhi High Court set aside an arbitral award that granted extra money to a contractor for using more cement than the baseline in a lump-sum contract. The Court held that arbitral tribunals cannot

Litigation India Editorial 24 November 2026 1 min read O.M.P. (COMM) 361/2017

Story

Court sets aside arbitral award for payment of excess cement in lump-sum construction contract. — infographic summary

What this case means

The Delhi High Court set aside an arbitral award that granted extra money to a contractor for using more cement than the baseline in a lump-sum contract. The Court held that arbitral tribunals cannot ignore express contract terms or rewrite agreements to create new payment entitlements. It clarified that the principle of interpreting ambiguity against the drafter only applies when real ambiguity exists.

What the Supreme Court held

The High Court set aside the arbitral awards to the extent they granted compensation for M-30 cement consumption and established a 330 kg/cum baseline for that grade. The remaining findings of the awards were left undisturbed.

Case: DELHI DEVELOPMENT AUTHORITY versus B.G.SHIRKE CONSTRUCTIONS TECHNOLOGY PRIVATE LIMITED (2026) Citation: O.M.P. (COMM) 361/2017

Want the full legal reasoning, citations and case documents?

Read the full judgment analysis
Delhi Development Authority
B.G. Shirke Constructions
Arbitration and Conciliation Act 1996
Section 34
M-30 Grade Concrete
Cement Consumption
Lump-sum Contract
Contra Proferentem
34, Arbitration and Conciliation Act, 1996
73, Indian Contract Act, 1872
Arbitration / Construction Law
Supreme Court legal news
Supreme Court judgment today
latest Supreme Court news

More in Arbitration / Construction Law

Delhi High Court Upholds Arbitration Award for Highway Project Delay Costs Against NHAI
Arbitration / Construction Law
23 Nov 2026

Delhi High Court Upholds Arbitration Award for Highway Project Delay Costs Against NHAI

The Delhi High Court dismissed a challenge by NHAI against an arbitration award that granted over ₹15 crore to a contractor for a 374-day delay. The court ruled that if a delay is the employer's fault

Read article
Litigation India

Insight First, Action Next. A public-service initiative to make justice understandable for every Indian.

contact@litigationindia.com

+91 9956486585

New Delhi, India

Quick Links

  • Updates
  • Legal Help
  • SC Lawyers
  • Resources for Litigants and Lawyers
  • Insights
  • Team
  • About

© 2026 Litigation India. All rights reserved.