The Delhi High Court dismissed a challenge by NHAI against an arbitration award that granted over ₹15 crore to a contractor for a 374-day delay. The court ruled that if a delay is the employer's fault, the contractor is entitled to actual additional costs beyond standard price escalation. It emphasized that courts cannot interfere with a tribunal's reasonable interpretation of a contract.
What the Supreme Court held
The Court dismissed NHAI's petition under Section 34, upholding the majority award. It ordered NHAI to pay the awarded sum for material costs, plant/equipment stay, and overheads, along with 10% interest compounded monthly.
Case: National Highways Authority of India vs. BSCPL Infrastructure Limited (2026) Citation: O.M.P. (COMM) 168/2016