Story

What this case means
NOIDA leased a plot to a developer but failed to provide the promised main access road due to encroachments. The Supreme Court ruled that the developer cannot be penalized with interest charges for construction delays caused by the government's failure. This ensures government bodies remain accountable for delivering promised infrastructure.
What the Supreme Court held
The Supreme Court dismissed NOIDA's appeal and upheld the High Court's directions. NOIDA was ordered to grant the 'Zero Period' benefits, issue a fresh demand without penal interest within two weeks, and approve the revised building plan within four weeks.
Case: New Okhla Industrial Development Authority vs M/s Sunshine Trade Tower Private Limited (2026) Citation: 2026 INSC 975