What this case means
The Court decided that Power Grid Corporation of India Limited (PGCIL) could recover transmission charges for two Line-In Line-Out (LILO) transmission elements at Tuticorin Pooling Station from their commissioning dates until the generating company completed its Dedicated Transmission Line. The Court found the LILOs were essential parts of the transmission system approved under statutory planning and were actively used for power evacuation despite upstream transmission delays.
What the Supreme Court held
The Supreme Court allowed the appeals and restored the CERC's order. The Court held that PGCIL is entitled to recover transmission charges for the two LILOs from 04.01.2015 and 08.01.2015 (their respective commissioning dates) until 27.10.2016 (when the generating company's DTL became operational) on a non-Point of Connection (non-PoC) basis. The Court set aside the APTEL's order which had rejected the tariff claim and directed a remand for reconsideration of the Commercial Operation Date. The Court directed that the concept of 'beneficial use' was erroneous and that the LILOs, being part of the statutory transmission plan approved in Standing Committee Meetings, were essential infrastructure through which the generated power necessarily flowed.
Case: Power Grid Corporation of India Limited vs. Tamil Nadu Generation and Distribution Corporation Limited (TANGEDCO) & Ors. (2026) Citation: 2026 INSC 1237
Want the full legal reasoning, citations and case documents?
Read the full judgment analysis