Legal News
Energy Law / Electricity Tariff Regulation

Must a power company pay transmission charges for transmission elements actually used but not yet connected to its dedicated line?

PGCIL entitled to transmission charges for LILOs from commissioning until DTL establishment.

The Court decided that Power Grid Corporation of India Limited (PGCIL) could recover transmission charges for two Line-In Line-Out (LILO) transmission elements at Tuticorin Pooling Station from their

Litigation India Editorial 21 November 2026 1 min read 2026 INSC 1237

Story

PGCIL entitled to transmission charges for LILOs from commissioning until DTL establishment. — infographic summary

What this case means

The Court decided that Power Grid Corporation of India Limited (PGCIL) could recover transmission charges for two Line-In Line-Out (LILO) transmission elements at Tuticorin Pooling Station from their commissioning dates until the generating company completed its Dedicated Transmission Line. The Court found the LILOs were essential parts of the transmission system approved under statutory planning and were actively used for power evacuation despite upstream transmission delays.

What the Supreme Court held

The Supreme Court allowed the appeals and restored the CERC's order. The Court held that PGCIL is entitled to recover transmission charges for the two LILOs from 04.01.2015 and 08.01.2015 (their respective commissioning dates) until 27.10.2016 (when the generating company's DTL became operational) on a non-Point of Connection (non-PoC) basis. The Court set aside the APTEL's order which had rejected the tariff claim and directed a remand for reconsideration of the Commercial Operation Date. The Court directed that the concept of 'beneficial use' was erroneous and that the LILOs, being part of the statutory transmission plan approved in Standing Committee Meetings, were essential infrastructure through which the generated power necessarily flowed.

Case: Power Grid Corporation of India Limited vs. Tamil Nadu Generation and Distribution Corporation Limited (TANGEDCO) & Ors. (2026) Citation: 2026 INSC 1237

Want the full legal reasoning, citations and case documents?

Read the full judgment analysis
LILO
Line-In Line-Out
transmission tariff
Commercial Operation Date
CERC
Electricity Act 2003
Tuticorin Pooling Station
Dedicated Transmission Line
Power Grid Corporation
TANGEDCO
Sections 2, 10, 25, 26, 27, 29, 30, 31, 38, 39, 42, 61, 62, 70, 73, Electricity Act, 2003
Regulations 3(53), 4, 4(3)(ii), 12(2), 43, Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014
Regulation 43, Central Electricity Authority (Measures Related to Safety and Electricity Supply) Regulations, 2010
Energy Law / Electricity Tariff Regulation
Litigation India

Insight First, Action Next. A public-service initiative to make justice understandable for every Indian.

contact@litigationindia.com

+91 9956486585

New Delhi, India

Quick Links

  • Updates
  • Legal Help
  • SC Lawyers
  • Resources for Litigants and Lawyers
  • Insights
  • Team
  • About

© 2026 Litigation India. All rights reserved.