The Court set a strict timeline for completing a long-delayed public subway in Tamil Nadu and praised a local citizen for fighting for it.
What the Supreme Court held
The Supreme Court ordered the State to speed up land acquisition and the Railways to finish its part of the work within six months of getting the land. Both must file progress reports within eight months.
Case: Madurai Farooq Ahmed vs. The Principal Secretary to Government (2026) Citation: 2026 INSC 903