Does consensual possession before formal notification prevent the lapse of land acquisition under Section 11-A?

Land acquisition proceedings lapse if compensation award is not made within two years of declaration.

The Court held that land acquisition lapses under Section 11-A of the 1894 Act if no award is passed within two years of the declaration. Possession taken before formal notice without using urgency po

Litigation India Editorial 28 November 2026 1 min read 2026 INSC 1296

Story

Land acquisition proceedings lapse if compensation award is not made within two years of declaration. — infographic summary

What this case means

The Court held that land acquisition lapses under Section 11-A of the 1894 Act if no award is passed within two years of the declaration. Possession taken before formal notice without using urgency powers does not transfer ownership to the State. Consequently, the government must start a new acquisition process under current laws to keep the land.

What the Supreme Court held

The Supreme Court upheld the High Court's order, ruling that the acquisition proceedings lapsed under Section 11-A of the 1894 Act. It directed the appellant to initiate fresh acquisition proceedings under the 2013 Act within three months and pay compensation based on the current law.

Case: Transmission Corporation of Andhra Pradesh Limited vs. Jaladi Sita Rama Koteswara Rao & Ors. (2026) Citation: 2026 INSC 1296

Want the full legal reasoning, citations and case documents?

Read the full judgment analysis
Transmission Corporation of Andhra Pradesh Limited
Jaladi Sita Rama Koteswara Rao
Land Acquisition Act 1894
Section 11-A
Section 17
Consensual possession
Lapse of acquisition
Fresh acquisition
2013 Act
Article 300-A
Section 11-A, Land Acquisition Act 1894
Section 17, Land Acquisition Act 1894
Article 300-A, Constitution of India
Civil Law / Land Acquisition

More in Civil Law / Land Acquisition

Last publication date under Section 4(1) determines 12 percent additional compensation under Section 23(1A)
Civil Law / Land Acquisition
28 Nov 2026

Last publication date under Section 4(1) determines 12 percent additional compensation under Section 23(1A)

The Court ruled that for calculating the 12% additional compensation under Section 23(1A) of the Land Acquisition Act, the date of publication is the last of the three prescribed modes. While the firs

Read article
Full court fees must be paid when challenging extra land acquisition benefits in appeal
Civil Law / Land Acquisition
1 Aug 2026

Full court fees must be paid when challenging extra land acquisition benefits in appeal

This case was about whether a company must pay full percentage-based court fees when challenging only extra benefits like interest and solatium. The Supreme Court decided that these benefits are a cor

Read article
Litigation India

Insight First, Action Next. A public-service initiative to make justice understandable for every Indian.

contact@litigationindia.com

+91 9956486585

New Delhi, India

Quick Links

  • Updates
  • Legal Help
  • SC Lawyers
  • Resources for Litigants and Lawyers
  • Insights
  • Team
  • About

© 2026 Litigation India. All rights reserved.