What this case means
A contractor's running bills from three separate road contracts were blocked by the government to recover alleged overpayments under two different, earlier contracts. The Supreme Court held this cross-contract recovery was unauthorised by any contractual clause and violated natural justice principles. The Court quashed the recovery order and directed refund with 6% interest.
What the Supreme Court held
The Supreme Court quashed the recovery order dated 27.09.2025 and directed the government to release Rs.84,17,003/- to the appellant with 6% interest per annum from 27.09.2025 till actual payment. The Court clarified that lawful recovery proceedings for the earlier works and the criminal case remain unaffected.
Case: M/S Awadhesh Singh Gautam vs. State of Chhattisgarh & Ors. (2026) Citation: 2026 INSC 1072