Can a Court modify an arbitral award under Section 37 solely because additional work costs exceeded 70% of the contract?

Courts cannot modify arbitral awards based on subjective shock over high additional work costs.

The Supreme Court ruled that under Section 37 of the Arbitration Act, courts cannot reduce a financial award just because the cost of additional work seems high compared to the original contract. If a

Litigation India Editorial 22 November 2026 1 min read 2026 INSC 1238

Story

Courts cannot modify arbitral awards based on subjective shock over high additional work costs. — infographic summary

What this case means

The Supreme Court ruled that under Section 37 of the Arbitration Act, courts cannot reduce a financial award just because the cost of additional work seems high compared to the original contract. If an award is supported by evidence and is not perverse, it cannot be modified based on a judge's subjective sense of morality or justice.

What the Supreme Court held

The Supreme Court set aside the High Court's Division Bench judgment and restored the original arbitral award in full. It held that the modification made by the High Court was outside the jurisdiction of Section 37 of the Arbitration and Conciliation Act, 1996, as the award was based on valid evidence and was not perverse.

Case: M/s Marino Dredgeco Limited Versus The Board of Trustees of the Port of Kolkata (2026) Citation: 2026 INSC 1238

Want the full legal reasoning, citations and case documents?

Read the full judgment analysis
M/s Marino Dredgeco Limited
Port of Kolkata
Arbitration and Conciliation Act 1996
Section 37
Section 34
Dredging contract
Shocking the conscience
Additional work
Section 37, Arbitration and Conciliation Act, 1996
Section 34, Arbitration and Conciliation Act, 1996
Arbitration Law
Supreme Court legal news
Supreme Court judgment today
latest Supreme Court news

More in Arbitration Law

Courts cannot limit an arbitrator's power to decide their own jurisdiction over contract disputes
Arbitration Law
8 Sept 2026

Courts cannot limit an arbitrator's power to decide their own jurisdiction over contract disputes

A railway contractor's agreement was terminated, and the dispute went to an arbitrator. The High Court told the arbitrator to decide strictly as per contract terms, which threatened to stop the arbitr

Read article
National Projects Construction Corporation Ltd. vs. Ishvakoo (India) Pvt. Ltd.
Arbitration Law
11 Aug 2026

National Projects Construction Corporation Ltd. vs. Ishvakoo (India) Pvt. Ltd.

The Supreme Court ruled that even a losing party in arbitration can ask for court protection under Section 9 to prevent the other side from keeping disputed money unfairly.

Read article
Litigation India

Insight First, Action Next. A public-service initiative to make justice understandable for every Indian.

contact@litigationindia.com

+91 9956486585

New Delhi, India

Quick Links

  • Updates
  • Legal Help
  • SC Lawyers
  • Resources for Litigants and Lawyers
  • Insights
  • Team
  • About

© 2026 Litigation India. All rights reserved.