What this case means
NEEPCO challenged an arbitral award granting pre-reference interest to a contractor. The Supreme Court held that Clause 54 of the contract expressly bars interest on delayed payments, unlike a narrower clause considered in an earlier precedent. The Court set aside the High Court order restoring such interest, confirming that a clear contractual bar overrides the arbitrator's statutory power under Section 31(7)(a).
What the Supreme Court held
The Supreme Court allowed NEEPCO's appeal and set aside the High Court's judgment to the extent it restored pre-reference interest. The Court held that Clause 54 of the GCC, by separately and expressly barring interest on delayed payments, is a complete contractual bar under the 1996 Act and falls within the line of authority in Sayeed Ahmed and THDC-II, not Harish Chandra. There was no order as to costs.
Case: North Eastern Electric Power Corporation Limited (NEEPCO) vs Astra Construction Private Limited (2026) Citation: 2026 INSC 1036
Want the full legal reasoning, citations and case documents?
Read the full judgment analysis