All insights

Does Clause 54 of the GCC bar an arbitrator from awarding pre-reference interest?

Contractual Clause Bars Pre-Reference Interest in Arbitration Awards

NEEPCO challenged an arbitral award granting pre-reference interest to a contractor. The Supreme Court held that Clause 54 of the contract expressly bars interest on delayed payments, unlike a narrowe

Litigation India Editorial 22 September 2026 1 min read 2026 INSC 1036

Story

Case at a glance1 / 6

Supreme Court of India

Contractual Clause 54 Bars Pre-Reference Interest in Arbitration

NEEPCO vs Astra Construction Private Limited — 2026 INSC 1036

Court: Supreme Court of India; Date: 22 September 2026Bench: Justice Pamidighantam Sri Narasimha and Justice Alok AradheArea of law: Arbitration Law — interest on arbitral awards, construction contractsContract for gas turbine power project civil works, Tripura, valued at Rs. 17 crores
Contractual Clause Bars Pre-Reference Interest in Arbitration Awards · 2026 INSC 10362026-09-22T16:41:38.447117+00:00
The legal question2 / 6

Does Clause 54 Bar Pre-Reference Interest in Arbitration?

The core dispute: which precedent governs Clause 54 of the GCC?

  • Appellant: Clause 54 bars pre-reference interest; Sayeed Ahmed and THDC-I govern, not Harish Chandra.
  • Appellant: Plea was specifically raised in Statement of Defence; no waiver occurred.
  • Respondent: Clause 54 is identical to Harish Chandra clause; bar is limited to dispute-related money.
  • Intervenor: Clause 54 does not bar interest on damages; residuary words take colour from preceding language.
Contractual Clause Bars Pre-Reference Interest in Arbitration Awards · 2026 INSC 10362026-09-22T16:41:38.447117+00:00
Statutory comparison3 / 6

Clause 54 vs Harish Chandra Clause: A Critical Difference

The wording difference that determines the legal outcome

Legal SubjectClause 54 (Present Case)Harish Chandra Clause (1999)
Interest bar on dispute-related moneyYes — expressly barredYes — expressly barred
Interest bar on delayed payment (independent ground)Yes — 'any delay on the part of Engineer-in-Charge making periodical or final payments' added as separate ground joined by 'or'No — delay in payment not a separate, independent ground
Residuary words 'in any other respect whatsoever'Follows two independent bars; covers broader groundConfined to dispute-related bar only
Applicable precedentSayeed Ahmed (2009), THDC-II (2019) — complete barHarish Chandra (1999) — limited bar
The addition of 'delay in payment' as an independent bar is what makes Clause 54 a complete exclusion of pre-reference interest.
Contractual Clause Bars Pre-Reference Interest in Arbitration Awards · 2026 INSC 10362026-09-22T16:41:38.447117+00:00
The Court's reasoning4 / 6

Court's Reasoning: Step by Step

From statutory framework to contract construction to conclusion

  1. 1Step 1: Under the 1996 Act, Section 31(7)(a) makes the arbitrator's power to grant interest subject to the parties' agreement.
  2. 2Step 2: Pre-reference interest is substantive law; a clear contractual bar suffices to exclude it under the 1996 Act.
  3. 3Step 3: Clause 54 bars interest on two independent grounds: (i) dispute-related money AND (ii) delayed payment — unlike the Harish Chandra clause.
  4. 4Step 4: Clauses with the same dual-bar structure in Sayeed Ahmed (2009) and THDC-II (2019) were held to be complete bars.
  5. 5Step 5: Therefore, Clause 54 is a complete bar; the Tribunal exceeded its jurisdiction; the High Court erred in restoring pre-reference interest.
Contractual Clause Bars Pre-Reference Interest in Arbitration Awards · 2026 INSC 10362026-09-22T16:41:38.447117+00:00
The verdict5 / 6

The Supreme Court's Verdict

Appeal allowed; pre-reference interest award set aside

  • The Fact: Clause 54 of the GCC expressly bars interest on both dispute-related money and delayed payments as independent grounds.
  • The Law: Under Section 31(7)(a) of the 1996 Act, a contractual bar on interest overrides the arbitrator's statutory power; Sayeed Ahmed and THDC-II govern.
  • The Result: The High Court's judgment restoring pre-reference interest is set aside; the Arbitral Tribunal exceeded its jurisdiction.
Appeal allowed. High Court judgment restoring pre-reference interest is set aside. No order as to costs.
Contractual Clause Bars Pre-Reference Interest in Arbitration Awards · 2026 INSC 10362026-09-22T16:41:38.447117+00:00
Why it matters6 / 6

What This Means for You

Practical significance for contractors, government agencies and arbitration parties

  • Contractors must read interest-bar clauses carefully; a separate mention of delayed payment as a bar can shut out interest claims entirely.
  • Under the 1996 Arbitration Act, even a general contractual bar on interest — not specifically addressed to the arbitrator — is legally effective.
  • The 1940 Act's strict-construction approach to interest bars no longer applies under the 1996 Act; party autonomy now prevails.
  • Government and public sector agencies can rely on broadly drafted interest-exclusion clauses to resist pre-reference interest in arbitration.
Under the 1996 Act, a clear contractual bar on interest binds the arbitrator — even if the clause does not mention arbitration specifically.
Contractual Clause Bars Pre-Reference Interest in Arbitration Awards · 2026 INSC 10362026-09-22T16:41:38.447117+00:00
Contractual Clause Bars Pre-Reference Interest in Arbitration Awards — infographic summary

What this case means

NEEPCO challenged an arbitral award granting pre-reference interest to a contractor. The Supreme Court held that Clause 54 of the contract expressly bars interest on delayed payments, unlike a narrower clause considered in an earlier precedent. The Court set aside the High Court order restoring such interest, confirming that a clear contractual bar overrides the arbitrator's statutory power under Section 31(7)(a).

What the Supreme Court held

The Supreme Court allowed NEEPCO's appeal and set aside the High Court's judgment to the extent it restored pre-reference interest. The Court held that Clause 54 of the GCC, by separately and expressly barring interest on delayed payments, is a complete contractual bar under the 1996 Act and falls within the line of authority in Sayeed Ahmed and THDC-II, not Harish Chandra. There was no order as to costs.

Case: North Eastern Electric Power Corporation Limited (NEEPCO) vs Astra Construction Private Limited (2026) Citation: 2026 INSC 1036

Want the full legal reasoning, citations and case documents?

Read the full judgment analysis
NEEPCO
Astra Construction
pre-reference interest
Clause 54 GCC
Arbitration and Conciliation Act 1996
Section 31(7)
Sayeed Ahmed
Harish Chandra
public works contracts
interest bar clause
Section 31(7)(a) and (b), Section 34, Section 37, Arbitration and Conciliation Act, 1996
General provisions on arbitrator's power to award interest, Arbitration Act, 1940
Section 3, Section 2(b), Interest Act, 1978
Arbitration Law / Contract Law / Interest on Arbitral Awards