What this case means
A developer and landowners disputed a development-cum-sale agreement, and a majority arbitral award granted specific performance with enhanced consideration. The Supreme Court held the award was patently illegal as the arbitrators rewrote the contract terms rather than applying them, violating Section 28(3) of the Arbitration and Conciliation Act, 1996. The Court set aside the award but directed the landowners to refund amounts received with 9% simple interest.
What the Supreme Court held
The Supreme Court dismissed the appeals and upheld the High Court's judgment setting aside the majority arbitral award, finding it violated Section 28(3) of the Arbitration and Conciliation Act, 1996, as the arbitrators rewrote the contract terms rather than applying them. Exercising power under Article 142 of the Constitution, the Court directed the respondents to refund all amounts received from the appellant under the agreement with simple interest at 9% per annum from the date of each payment till actual refund. The appellant's amounts lying in deposit with the courts were also directed to be returned with accrued interest.
Case: Shreeram Builders vs. Upendra Kantilal Thanawala and others (2026) Citation: 2026 INSC 1176
Want the full legal reasoning, citations and case documents?
Read the full judgment analysis